Lime Creek 161 kV Substation (J1176)

Lime Creek 161 kV Substation is a 145.0 MW wind interconnection project in Cerro Gordo County,Worth County, Iowa with a current status of withdrawn. It is proposed to connect at Lime Creek 161 kV Substation.

145.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameLime Creek 161 kV Substation
Queue IDJ1176
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity145.0 MW
StateIowa
CountyCerro Gordo County,Worth County
Point of interconnectionLime Creek 161 kV Substation
Requested (queue) date2018-03-12
Proposed in-service date2021-10-31
Operational date2021-10-31
Withdrawn date2019-08-15
Developer
Utility / transmission ownerITC MIDWEST

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.