Line tap on Superior-Wayne 120kV line at 42.275480, -83.628250 (J3654)

Line tap on Superior-Wayne 120kV line at 42.275480, -83.628250 is a 150.0 MW battery interconnection project in Washtenaw, Michigan with a current status of operational. It is proposed to connect at Line tap on Superior-Wayne 120kV line at 42.275480, -83.628250.

150.0 MWCapacity
OperationalStatus
Market
BatteryTechnology

Project facts

Canonical nameLine tap on Superior-Wayne 120kV line at 42.275480, -83.628250
Queue IDJ3654
Statusoperational
Source statusActive
Market
TechnologyBattery
Capacity150.0 MW
StateMichigan
CountyWashtenaw
Point of interconnectionLine tap on Superior-Wayne 120kV line at 42.275480, -83.628250
Requested (queue) date2024-04-05
Proposed in-service date2028-06-01
Operational date2028-06-01
Withdrawn date
Developer
Utility / transmission ownerITC MIDWEST

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.