Long Canyon is a 7.4 MW other interconnection project in West Wendover, Nevada with a current status of withdrawn. It is proposed to connect at BPA's West Wendover Substation.

7.4 MWCapacity
WithdrawnStatus
NVMarket
OtherTechnology

Project facts

Canonical nameLong Canyon
Queue IDL0364
Statuswithdrawn
Source statusWITHDRAWN
MarketNV
TechnologyOther
Capacity7.4 MW
StateNevada
CountyWest Wendover
Point of interconnectionBPA's West Wendover Substation
Requested (queue) date2013-09-17
Proposed in-service date2017-10-01
Operational date
Withdrawn date
DeveloperWells Rural Electric Company
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.