Machias Wind Farm (0170)

Machias Wind Farm is a 90.0 MW wind interconnection project in Cattaraugus, New York with a current status of withdrawn. It is proposed to connect at Homer Hill-Gardenville 115kV.

90.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameMachias Wind Farm
Queue ID0170
Statuswithdrawn
Source status0
Market
TechnologyWind
Capacity90.0 MW
StateNew York
CountyCattaraugus
Point of interconnectionHomer Hill-Gardenville 115kV
Requested (queue) date2005-02-08
Proposed in-service date2006-10-11
Operational date
Withdrawn date
DeveloperMachias Wind Farm, LLC
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.