Magee 161 - White Oak 161.0kV (J2887)

Magee 161 - White Oak 161.0kV is a 50.0 MW battery interconnection project in Simpson, Mississippi with a current status of withdrawn. It is proposed to connect at Magee 161 - White Oak 161.0kV.

50.0 MWCapacity
WithdrawnStatus
—Market
BatteryTechnology

Project facts

Canonical nameMagee 161 - White Oak 161.0kV
Queue IDJ2887
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyBattery
Capacity50.0 MW
StateMississippi
CountySimpson
Point of interconnectionMagee 161 - White Oak 161.0kV
Requested (queue) date2022-09-13
Proposed in-service date2027-10-01
Operational date2027-10-01
Withdrawn date2025-07-31
Developer—
Utility / transmission ownerCOOPERATIVE ENERGY

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-31phasePhase 2Phase 3low
2026-10-14phasePhase 1Phase 2low
2026-07-29new_project—withdrawnhigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata