Maid 161kV substation (GEN-2019-002)

Maid 161kV substation is a 100.0 MW battery interconnection project in Mayes, Oklahoma with a current status of active. It is proposed to connect at Maid 161kV substation.

100.0 MWCapacity
ActiveStatus
OKMarket
BatteryTechnology

Project facts

Canonical nameMaid 161kV substation
Queue IDGEN-2019-002
Statusactive
Source statusIA FULLY EXECUTED/ON SCHEDULE
MarketOK
TechnologyBattery
Capacity100.0 MW
StateOklahoma
CountyMayes
Point of interconnectionMaid 161kV substation
Requested (queue) date2018-11-26
Proposed in-service date2027-11-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerGRDA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectactivehigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.