Manchester Street Station increase (336)

Manchester Street Station increase is a 471.0 MW gas interconnection project in Providence, Rhode Island with a current status of operational. It is proposed to connect at GRID 115 kV Franklin substation.

471.0 MWCapacity
OperationalStatus
RIMarket
GasTechnology

Project facts

Canonical nameManchester Street Station increase
Queue ID336
Statusoperational
Source statusC
MarketRI
TechnologyGas
Capacity471.0 MW
StateRhode Island
CountyProvidence
Point of interconnectionGRID 115 kV Franklin substation
Requested (queue) date2010-05-14
Proposed in-service date
Operational date2010-08-02
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.