Maplewood Energy Storage is a 250.0 MW battery interconnection project in Albany, New York with a current status of withdrawn. It is proposed to connect at Maplewood - Menands 115kV Line #19 & Maplewood - Reynolds 115kV Line #31.

250.0 MWCapacity
WithdrawnStatus
FMarket
BatteryTechnology

Project facts

Canonical nameMaplewood Energy Storage
Queue ID1233
Statuswithdrawn
Source status0
MarketF
TechnologyBattery
Capacity250.0 MW
StateNew York
CountyAlbany
Point of interconnectionMaplewood - Menands 115kV Line #19 & Maplewood - Reynolds 115kV Line #31
Requested (queue) date2021-08-20
Proposed in-service date2023-10-31
Operational date
Withdrawn date
DeveloperACE Development Company, LLC
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.