Masked (021177)
Masked is a 741.0 MW gas interconnection project in Cherokee, South Carolina with a current status of withdrawn. It is proposed to connect at Riverview.
741.0 MWCapacity
WithdrawnStatus
SCMarket
GasTechnology
Project facts
| Canonical name | Masked |
|---|---|
| Queue ID | 021177 |
| Status | withdrawn |
| Source status | Withdrawn |
| Market | SC |
| Technology | Gas |
| Capacity | 741.0 MW |
| State | South Carolina |
| County | Cherokee |
| Point of interconnection | Riverview |
| Requested (queue) date | 2018-03-05 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Duke Energy Progress |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28
Provenance: duke-dec-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata