Masked (069510)

Masked is a 40.0 MW solar interconnection project in Greenwood, South Carolina with a current status of withdrawn. It is proposed to connect at Greenwood W/B 100kV.

40.0 MWCapacity
WithdrawnStatus
SCMarket
SolarTechnology

Project facts

Canonical nameMasked
Queue ID069510
Statuswithdrawn
Source statusWithdrawn
MarketSC
TechnologySolar
Capacity40.0 MW
StateSouth Carolina
CountyGreenwood
Point of interconnectionGreenwood W/B 100kV
Requested (queue) date2020-03-06
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerDuke Energy Progress

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: duke-dec-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata