Masked (008609)

Masked is a 80.0 MW solar interconnection project in Clarendon, South Carolina with a current status of withdrawn. It is proposed to connect at Sumter Canadys 230 kV Line.

80.0 MWCapacity
WithdrawnStatus
SCMarket
SolarTechnology

Project facts

Canonical nameMasked
Queue ID008609
Statuswithdrawn
Source statusWithdrawn
MarketSC
TechnologySolar
Capacity80.0 MW
StateSouth Carolina
CountyClarendon
Point of interconnectionSumter Canadys 230 kV Line
Requested (queue) date2016-10-13
Proposed in-service date
Operational date
Withdrawn date
Developer
Utility / transmission ownerDuke Energy Progress

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28

Provenance: duke-dep-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.