Meredith (C26-0039)

Meredith is a 118.0 MW battery interconnection project in Richmond, New York with a current status of active. It is proposed to connect at Fresh Kills 138 kV substation.

118.0 MWCapacity
ActiveStatus
JMarket
BatteryTechnology

Project facts

Canonical nameMeredith
Queue IDC26-0039
Statusactive
Source status2
MarketJ
TechnologyBattery
Capacity118.0 MW
StateNew York
CountyRichmond
Point of interconnectionFresh Kills 138 kV substation
Requested (queue) date2026-08-27
Proposed in-service date—
Operational date—
Withdrawn date—
DeveloperOrenda Power LLC
Utility / transmission ownerCONED

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-14new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata