MEXICO WIND (178B)

MEXICO WIND is a 500.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at Imperial Valley 230kV Substation.

500.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameMEXICO WIND
Queue ID178B
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologyWind
Capacity500.0 MW
StateMX
CountyMexicali/ensenada/tecate
Point of interconnectionImperial Valley 230kV Substation
Requested (queue) date2007-02-28
Proposed in-service date
Operational date
Withdrawn date2011-03-31
Developer
Utility / transmission ownerSDGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata