Milan Tap to Gill 138 kV line (GEN-2023-113)

Milan Tap to Gill 138 kV line is a 117.0 MW solar interconnection project in Sumner, Kansas with a current status of withdrawn. It is proposed to connect at Milan Tap to Gill 138 kV line.

117.0 MWCapacity
WithdrawnStatus
KSMarket
SolarTechnology

Project facts

Canonical nameMilan Tap to Gill 138 kV line
Queue IDGEN-2023-113
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologySolar
Capacity117.0 MW
StateKansas
CountySumner
Point of interconnectionMilan Tap to Gill 138 kV line
Requested (queue) date2023-10-02
Proposed in-service date2029-12-31
Operational date
Withdrawn date2023-10-19
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata