Minco 345kV substation (GEN-2017-067)

Minco 345kV substation is a 200.2 MW solar interconnection project in Caddo County, Oklahoma with a current status of withdrawn. It is proposed to connect at Minco 345kV substation.

200.2 MWCapacity
WithdrawnStatus
OKMarket
SolarTechnology

Project facts

Canonical nameMinco 345kV substation
Queue IDGEN-2017-067
Statuswithdrawn
Source statusWITHDRAWN
MarketOK
TechnologySolar
Capacity200.2 MW
StateOklahoma
CountyCaddo County
Point of interconnectionMinco 345kV substation
Requested (queue) date2017-05-30
Proposed in-service date
Operational date
Withdrawn date2020-12-07
Developer
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.