Mingo 345kV (GEN-2015-065)

Mingo 345kV is a 202.4 MW wind interconnection project in Thomas County, Kansas with a current status of operational. It is proposed to connect at Mingo 345kV.

202.4 MWCapacity
OperationalStatus
KSMarket
WindTechnology

Project facts

Canonical nameMingo 345kV
Queue IDGEN-2015-065
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketKS
TechnologyWind
Capacity202.4 MW
StateKansas
CountyThomas County
Point of interconnectionMingo 345kV
Requested (queue) date2015-10-07
Proposed in-service date
Operational date2017-11-01
Withdrawn date
Developer
Utility / transmission ownerSUNC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata