MISO Queue Project E0004 — Battery in Saginaw, Michigan

MISO Queue Project E0004 — Battery in Saginaw, Michigan is a 104.3 MW battery interconnection project in Saginaw, Michigan with a current status of active. It is proposed to connect at Bullock-Signaw River 138kV.

104.3 MWCapacity
ActiveStatus
MISOMarket
BatteryTechnology

Project facts

Canonical nameMISO Queue Project E0004 — Battery in Saginaw, Michigan
Queue IDE0004
Statusactive
Source statusactive
MarketMISO
TechnologyBattery
Capacity104.3 MW
StateMichigan
CountySaginaw
Point of interconnectionBullock-Signaw River 138kV
Requested (queue) date2025-08-07
Proposed in-service date2027-09-01
Operational date
Withdrawn date
DeveloperHackett Energy Storage LLC
Utility / transmission ownerConsumers Energy Co - (MI)

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.