Mistral Wind Alternative (0771)

Mistral Wind Alternative is a 20.0 MW wind interconnection project in Genesee, New York with a current status of withdrawn. It is proposed to connect at N. Akron - Attica 34.5 kV.

20.0 MWCapacity
WithdrawnStatus
BMarket
WindTechnology

Project facts

Canonical nameMistral Wind Alternative
Queue ID0771
Statuswithdrawn
Source status0
MarketB
TechnologyWind
Capacity20.0 MW
StateNew York
CountyGenesee
Point of interconnectionN. Akron - Attica 34.5 kV
Requested (queue) date2018-10-10
Proposed in-service date2020-01-31
Operational date
Withdrawn date
DeveloperMistral Wind LLC
Utility / transmission ownerNM-NG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.