MO Queue Project GI-72 — Solar in New Madrid County, Missouri

MO Queue Project GI-72 — Solar in New Madrid County, Missouri is a 300.0 MW solar interconnection project in New Madrid County, Missouri with a current status of withdrawn. It is proposed to connect at New Madrid to St Francis 345 kV.

300.0 MWCapacity
WithdrawnStatus
MOMarket
SolarTechnology

Project facts

Canonical nameMO Queue Project GI-72 — Solar in New Madrid County, Missouri
Queue IDGI-72
Statuswithdrawn
Source statusWithdrawn
MarketMO
TechnologySolar
Capacity300.0 MW
StateMissouri
CountyNew Madrid County
Point of interconnectionNew Madrid to St Francis 345 kV
Requested (queue) date2018-11-19
Proposed in-service date2021-10-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerAssociated Electric Cooperative, Inc.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28

Provenance: aeci-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata