MO Queue Project GI-95 — Wind in Dade County, Missouri
MO Queue Project GI-95 — Wind in Dade County, Missouri is a 247.0 MW wind interconnection project in Dade County, Missouri with a current status of active. It is proposed to connect at Jasper-Morgan 345 kV.
247.0 MWCapacity
ActiveStatus
MOMarket
WindTechnology
Project facts
| Canonical name | MO Queue Project GI-95 — Wind in Dade County, Missouri |
|---|---|
| Queue ID | GI-95 |
| Status | active |
| Source status | GIA |
| Market | MO |
| Technology | Wind |
| Capacity | 247.0 MW |
| State | Missouri |
| County | Dade County |
| Point of interconnection | Jasper-Morgan 345 kV |
| Requested (queue) date | 2020-12-04 |
| Proposed in-service date | 2026-12-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Associated Electric Cooperative, Inc. |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | active | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-28
Provenance: aeci-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata