Monroe ERAS (E0018)

Monroe ERAS is a 432.0 MW battery interconnection project in Monroe, Michigan with a current status of active. It is proposed to connect at Monroe-Bayshore 315kV.

432.0 MWCapacity
ActiveStatus
MISOMarket
BatteryTechnology

Project facts

Canonical nameMonroe ERAS
Queue IDE0018
Statusactive
Source statusactive
MarketMISO
TechnologyBattery
Capacity432.0 MW
StateMichigan
CountyMonroe
Point of interconnectionMonroe-Bayshore 315kV
Requested (queue) date2025-08-06
Proposed in-service date2028-06-02
Operational date
Withdrawn date
DeveloperDTE Electric
Utility / transmission ownerDTE Electric Company

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.