Moonstone Energy 2, LLC (719)

Moonstone Energy 2, LLC is a 100.0 MW solar+battery interconnection project in Blaine, Idaho with a current status of active. It is proposed to connect at Moonstone Substation 138kV.

100.0 MWCapacity
ActiveStatus
IDMarket
Solar+BatteryTechnology

Project facts

Canonical nameMoonstone Energy 2, LLC
Queue ID719
Statusactive
Source statusConstruction
MarketID
TechnologySolar+Battery
Capacity100.0 MW
StateIdaho
CountyBlaine
Point of interconnectionMoonstone Substation 138kV
Requested (queue) date2023-06-01
Proposed in-service date2028-06-01
Operational date
Withdrawn date
DeveloperMoonstone Energy 2, LLC
Utility / transmission ownerIdaho Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: idahopower-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata