Moreland 138kV Substation (GEN-2016-020)

Moreland 138kV Substation is a 148.4 MW wind interconnection project in Woodward County, Oklahoma with a current status of operational. It is proposed to connect at Moreland 138kV Substation.

148.4 MWCapacity
OperationalStatus
OKMarket
WindTechnology

Project facts

Canonical nameMoreland 138kV Substation
Queue IDGEN-2016-020
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologyWind
Capacity148.4 MW
StateOklahoma
CountyWoodward County
Point of interconnectionMoreland 138kV Substation
Requested (queue) date2016-04-01
Proposed in-service date
Operational date2018-12-31
Withdrawn date
Developer
Utility / transmission ownerWFEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.