MS Queue Project 569 — Gas in Lowndes, Mississippi

MS Queue Project 569 — Gas in Lowndes, Mississippi is a 515.0 MW gas interconnection project in Lowndes, Mississippi with a current status of active. It is proposed to connect at Lowndes 161kV Substation.

515.0 MWCapacity
ActiveStatus
MSMarket
GasTechnology

Project facts

Canonical nameMS Queue Project 569 — Gas in Lowndes, Mississippi
Queue ID569
Statusactive
Source statusFacilities Study
MarketMS
TechnologyGas
Capacity515.0 MW
StateMississippi
CountyLowndes
Point of interconnectionLowndes 161kV Substation
Requested (queue) date2023-06-20
Proposed in-service date2026-09-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerTennessee Valley Authority

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: tva-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata