MT Queue Project 390 — Solar+Battery in Yellowstone County, Montana

MT Queue Project 390 — Solar+Battery in Yellowstone County, Montana is a 500.0 MW solar+battery interconnection project in Yellowstone County, Montana with a current status of active. It is proposed to connect at 500kV at Broadview Substation.

500.0 MWCapacity
ActiveStatus
MTMarket
Solar+BatteryTechnology

Project facts

Canonical nameMT Queue Project 390 — Solar+Battery in Yellowstone County, Montana
Queue ID390
Statusactive
Source statusSigned Agreement
MarketMT
TechnologySolar+Battery
Capacity500.0 MW
StateMontana
CountyYellowstone County
Point of interconnection500kV at Broadview Substation
Requested (queue) date2020-08-13
Proposed in-service date2023-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerNorthWestern Energy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: northwestern-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.