National Grid Storage 186117 (186117)

National Grid Storage 186117 is a 2.5 MW battery interconnection project in Schenectady, New York with a current status of operational. It is proposed to connect at ROTTERDAM 138 / 36_32_13853.

2.5 MWCapacity
OperationalStatus
PattersonvilleMarket
BatteryTechnology

Project facts

Canonical nameNational Grid Storage 186117
Queue ID186117
Statusoperational
Source statusInterconnected
MarketPattersonville
TechnologyBattery
Capacity2.5 MW
StateNew York
CountySchenectady
Point of interconnectionROTTERDAM 138 / 36_32_13853
Requested (queue) date
Proposed in-service date
Operational date2020-12-31
Withdrawn date
Developer
Utility / transmission ownerNational Grid

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-05new_projectoperationalhigh

Explore related data

Source last checked2026-08-05
Data last materially changed2026-08-05
Page data generated2026-08-28

Provenance: ny-storage. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.