Neosho - LaCynge 345 kV Line (GEN-2023-231)

Neosho - LaCynge 345 kV Line is a 310.0 MW wind interconnection project in Crawford, Kansas with a current status of withdrawn. It is proposed to connect at Neosho - LaCynge 345 kV Line.

310.0 MWCapacity
WithdrawnStatus
KSMarket
WindTechnology

Project facts

Canonical nameNeosho - LaCynge 345 kV Line
Queue IDGEN-2023-231
Statuswithdrawn
Source statusWITHDRAWN
MarketKS
TechnologyWind
Capacity310.0 MW
StateKansas
CountyCrawford
Point of interconnectionNeosho - LaCynge 345 kV Line
Requested (queue) date2023-10-02
Proposed in-service date2028-12-01
Operational date
Withdrawn date2025-08-25
Developer
Utility / transmission ownerEvergy

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata