Newington Gas Turbine Uprate (484)

Newington Gas Turbine Uprate is a 27.9 MW gas interconnection project in Rockingham, New Hampshire with a current status of operational. It is proposed to connect at Public Service New Hampshire Newington Switchyard - Gosling Road, Newington, NH.

27.9 MWCapacity
OperationalStatus
NHMarket
GasTechnology

Project facts

Canonical nameNewington Gas Turbine Uprate
Queue ID484
Statusoperational
Source statusC
MarketNH
TechnologyGas
Capacity27.9 MW
StateNew Hampshire
CountyRockingham
Point of interconnectionPublic Service New Hampshire Newington Switchyard - Gosling Road, Newington, NH
Requested (queue) date2014-12-04
Proposed in-service date
Operational date2015-10-30
Withdrawn date
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectoperationalhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.