Newport 161 kV Bus High Side of T91 XFRMR 161/69 kV (J3024)

Newport 161 kV Bus High Side of T91 XFRMR 161/69 kV is a 100.0 MW battery interconnection project in Louisa, Iowa with a current status of withdrawn. It is proposed to connect at Newport 161 kV Bus High Side of T91 XFRMR 161/69 kV.

100.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameNewport 161 kV Bus High Side of T91 XFRMR 161/69 kV
Queue IDJ3024
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity100.0 MW
StateIowa
CountyLouisa
Point of interconnectionNewport 161 kV Bus High Side of T91 XFRMR 161/69 kV
Requested (queue) date2022-09-12
Proposed in-service date2026-03-07
Operational date2026-03-07
Withdrawn date2023-03-27
Developer
Utility / transmission ownerITC MIDWEST

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.