NM Queue Project IA-PNM-2014-01 — Wind in an unlisted county, New Mexico
NM Queue Project IA-PNM-2014-01 — Wind in an unlisted county, New Mexico is a 200.0 MW wind interconnection project with a current status of withdrawn. It is proposed to connect at On the BB 345 kV line between Guadalupe and Taiban Guadalupe Cty, NM.
200.0 MWCapacity
WithdrawnStatus
NMMarket
WindTechnology
Project facts
| Canonical name | NM Queue Project IA-PNM-2014-01 — Wind in an unlisted county, New Mexico |
|---|---|
| Queue ID | IA-PNM-2014-01 |
| Status | withdrawn |
| Source status | — |
| Market | NM |
| Technology | Wind |
| Capacity | 200.0 MW |
| State | New Mexico |
| County | — |
| Point of interconnection | On the BB 345 kV line between Guadalupe and Taiban Guadalupe Cty, NM |
| Requested (queue) date | 2014-02-12 |
| Proposed in-service date | — |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Public Service Company of New Mexico |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-03 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: pnm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata