NM Queue Project IA-PNM-2026-12 — Solar+Battery in DeBaca County, New Mexico

NM Queue Project IA-PNM-2026-12 — Solar+Battery in DeBaca County, New Mexico is a 300.0 MW solar+battery interconnection project in DeBaca County, New Mexico with a current status of active. It is proposed to connect at 345 kV Blackwater Tie to Taiban Mesa line DeBaca County Energy Resource.

300.0 MWCapacity
ActiveStatus
NMMarket
Solar+BatteryTechnology

Project facts

Canonical nameNM Queue Project IA-PNM-2026-12 — Solar+Battery in DeBaca County, New Mexico
Queue IDIA-PNM-2026-12
Statusactive
Source status—
MarketNM
TechnologySolar+Battery
Capacity300.0 MW
StateNew Mexico
CountyDeBaca County
Point of interconnection345 kV Blackwater Tie to Taiban Mesa line DeBaca County Energy Resource
Requested (queue) date2026-08-24
Proposed in-service date—
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerPublic Service Company of New Mexico

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-07new_project—activehigh

Explore related data

Source last checked2026-10-05
Data last materially changed2026-10-05
Page data generated2026-10-11

Provenance: pnm-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata