Nuthatch Switching Substation (J2122)

Nuthatch Switching Substation is a 33.0 MW wind interconnection project in Franklin, Iowa with a current status of withdrawn. It is proposed to connect at Nuthatch Switching Substation.

33.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameNuthatch Switching Substation
Queue IDJ2122
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity33.0 MW
StateIowa
CountyFranklin
Point of interconnectionNuthatch Switching Substation
Requested (queue) date2021-08-04
Proposed in-service date2024-06-30
Operational date2024-06-30
Withdrawn date2026-06-22
Developer
Utility / transmission ownerITC MIDWEST

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata