NV Queue Project 26-00460 — Other in Pershing, Nevada is a 199.0 MW other interconnection project in Pershing, Nevada with a current status of active. It is proposed to connect at Buffalo Moutain 345kV.
199.0 MWCapacity
ActiveStatus
NVMarket
OtherTechnology
Project facts
| Canonical name | NV Queue Project 26-00460 — Other in Pershing, Nevada |
|---|---|
| Queue ID | 26-00460 |
| Status | active |
| Source status | In Study |
| Market | NV |
| Technology | Other |
| Capacity | 199.0 MW |
| State | Nevada |
| County | Pershing |
| Point of interconnection | Buffalo Moutain 345kV |
| Requested (queue) date | 2026-07-30 |
| Proposed in-service date | 2031-04-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | NV Energy (Nevada Power / Sierra Pacific Power) |
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-10 | new_project | — | active | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27
Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata