NV Queue Project Company MR — Wind in Lyon, Nevada

NV Queue Project Company MR — Wind in Lyon, Nevada is a 150.0 MW wind interconnection project in Lyon, Nevada with a current status of withdrawn. It is proposed to connect at Chukar 120 kV.

150.0 MWCapacity
WithdrawnStatus
NVMarket
WindTechnology

Project facts

Canonical nameNV Queue Project Company MR — Wind in Lyon, Nevada
Queue IDCompany MR
Statuswithdrawn
Source statusWithdrawn
MarketNV
TechnologyWind
Capacity150.0 MW
StateNevada
CountyLyon
Point of interconnectionChukar 120 kV
Requested (queue) date2022-03-24
Proposed in-service date2026-03-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerNV Energy (Nevada Power / Sierra Pacific Power)

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.