NV Queue Project Company ND — Solar+Battery in Lander, Nevada

NV Queue Project Company ND — Solar+Battery in Lander, Nevada is a 300.0 MW solar+battery interconnection project in Lander, Nevada with a current status of suspended. It is proposed to connect at Valmy - Falcon 345 kV.

300.0 MWCapacity
SuspendedStatus
NVMarket
Solar+BatteryTechnology

Project facts

Canonical nameNV Queue Project Company ND — Solar+Battery in Lander, Nevada
Queue IDCompany ND
Statussuspended
Source statusExecuted - Suspended
MarketNV
TechnologySolar+Battery
Capacity300.0 MW
StateNevada
CountyLander
Point of interconnectionValmy - Falcon 345 kV
Requested (queue) date2022-03-29
Proposed in-service date2030-12-31
Operational date
Withdrawn date
Developer
Utility / transmission ownerNV Energy (Nevada Power / Sierra Pacific Power)

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectsuspendedhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.