NY Hudson Fairview Ave Storage (1383)
NY Hudson Fairview Ave Storage is a 25.2 MW battery interconnection project in Columbia, New York with a current status of withdrawn. It is proposed to connect at Nassau - Hudson 34.5kV.
25.2 MWCapacity
WithdrawnStatus
FMarket
BatteryTechnology
Project facts
| Canonical name | NY Hudson Fairview Ave Storage |
|---|---|
| Queue ID | 1383 |
| Status | withdrawn |
| Source status | 0 |
| Market | F |
| Technology | Battery |
| Capacity | 25.2 MW |
| State | New York |
| County | Columbia |
| Point of interconnection | Nassau - Hudson 34.5kV |
| Requested (queue) date | 2022-05-05 |
| Proposed in-service date | 2022-11-30 |
| Operational date | — |
| Withdrawn date | — |
| Developer | Bluewave Storage Origination LLC |
| Utility / transmission owner | NM-NG |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.