NY Interconnection 7 (1438)

NY Interconnection 7 is a 270.0 MW wind interconnection project in Richmond, New York with a current status of withdrawn. It is proposed to connect at Goethals-Gowanus 345kV line break.

270.0 MWCapacity
WithdrawnStatus
JMarket
WindTechnology

Project facts

Canonical nameNY Interconnection 7
Queue ID1438
Statuswithdrawn
Source status0
MarketJ
TechnologyWind
Capacity270.0 MW
StateNew York
CountyRichmond
Point of interconnectionGoethals-Gowanus 345kV line break
Requested (queue) date2022-09-15
Proposed in-service date2024-05-31
Operational date
Withdrawn date
DeveloperNY Interconnection LLC
Utility / transmission ownerCONED

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata