OAK RIDGE (LA) - SWARTZ 115.0kV (J3600)

OAK RIDGE (LA) - SWARTZ 115.0kV is a 50.0 MW battery interconnection project in Morehouse, Louisiana with a current status of withdrawn. It is proposed to connect at OAK RIDGE (LA) - SWARTZ 115.0kV.

50.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameOAK RIDGE (LA) - SWARTZ 115.0kV
Queue IDJ3600
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity50.0 MW
StateLouisiana
CountyMorehouse
Point of interconnectionOAK RIDGE (LA) - SWARTZ 115.0kV
Requested (queue) date2024-04-16
Proposed in-service date2028-09-01
Operational date2028-09-01
Withdrawn date2025-09-29
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.