OK Queue Project GI-130 — Gas in Payne County, Oklahoma

OK Queue Project GI-130 — Gas in Payne County, Oklahoma is a 460.0 MW gas interconnection project in Payne County, Oklahoma with a current status of active. It is proposed to connect at Cleveland - Silver City 138 kV.

460.0 MWCapacity
ActiveStatus
OKMarket
GasTechnology

Project facts

Canonical nameOK Queue Project GI-130 — Gas in Payne County, Oklahoma
Queue IDGI-130
Statusactive
Source statusFS
MarketOK
TechnologyGas
Capacity460.0 MW
StateOklahoma
CountyPayne County
Point of interconnectionCleveland - Silver City 138 kV
Requested (queue) date2025-07-25
Proposed in-service date2030-11-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerAssociated Electric Cooperative, Inc.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: aeci-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata