Orient - Denny 345kV (J4006)

Orient - Denny 345kV is a 289.8 MW wind interconnection project in Ringgold, Iowa with a current status of operational. It is proposed to connect at Orient - Denny 345kV.

289.8 MWCapacity
OperationalStatus
Market
WindTechnology

Project facts

Canonical nameOrient - Denny 345kV
Queue IDJ4006
Statusoperational
Source statusActive
Market
TechnologyWind
Capacity289.8 MW
StateIowa
CountyRinggold
Point of interconnectionOrient - Denny 345kV
Requested (queue) date2025-05-07
Proposed in-service date2030-09-02
Operational date2030-09-02
Withdrawn date
Developer
Utility / transmission ownerMIDAMERICAN ENERGY CO.

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.