PACE Queue Project S0028 — Battery in Converse, Wyoming

PACE Queue Project S0028 — Battery in Converse, Wyoming is a 320.0 MW battery interconnection project in Converse, Wyoming with a current status of withdrawn. It is proposed to connect at Windstar substation.

320.0 MWCapacity
WithdrawnStatus
PACEMarket
BatteryTechnology

Project facts

Canonical namePACE Queue Project S0028 — Battery in Converse, Wyoming
Queue IDS0028
Statuswithdrawn
Source statusWithdrawn
MarketPACE
TechnologyBattery
Capacity320.0 MW
StateWyoming
CountyConverse
Point of interconnectionWindstar substation
Requested (queue) date2024-02-08
Proposed in-service date2026-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPacifiCorp

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-03new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: pacificorp-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata