PAHRUMP VALLEY SOLAR (FKA LATHROP WELLS 240MW) (908)

PAHRUMP VALLEY SOLAR (FKA LATHROP WELLS 240MW) is a 210.0 MW solar interconnection project in Nye, Nevada with a current status of withdrawn. It is proposed to connect at Crazy Eyes Tap 230kV.

210.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical namePAHRUMP VALLEY SOLAR (FKA LATHROP WELLS 240MW)
Queue ID908
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar
Capacity210.0 MW
StateNevada
CountyNye
Point of interconnectionCrazy Eyes Tap 230kV
Requested (queue) date2012-04-02
Proposed in-service date
Operational date
Withdrawn date2015-03-12
Developer
Utility / transmission ownerVEA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata