Peddler (J3220)

Peddler is a 200.0 MW battery interconnection project in Ionia, Michigan with a current status of withdrawn. It is proposed to connect at Peddler.

200.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical namePeddler
Queue IDJ3220
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity200.0 MW
StateMichigan
CountyIonia
Point of interconnectionPeddler
Requested (queue) date2024-08-05
Proposed in-service date2026-10-31
Operational date2026-10-31
Withdrawn date2025-08-01
Developer
Utility / transmission ownerMETC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-28
Data last materially changed2026-08-28
Page data generated2026-08-28

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata