PF Onsite BESS (70240_PFNON)

PF Onsite BESS is a 21.0 MW battery interconnection project in Luzerne, Pennsylvania with a current status of active.

21.0 MWCapacity
ActiveStatus
PJMMarket
BatteryTechnology

Project facts

Canonical namePF Onsite BESS
Queue ID70240_PFNON
Statusactive
Source status(L) Regulatory approvals pending. Not under construction
MarketPJM
TechnologyBattery
Capacity21.0 MW
StatePennsylvania
CountyLuzerne
Point of interconnection
Requested (queue) date
Proposed in-service date2027-06-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerPF Onsite Generation LLC

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-02new_projectactivehigh

Explore related data

Source last checked2026-08-03
Data last materially changed2026-08-03
Page data generated2026-08-27

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata