Pickens 230 kV Substation (J3139)

Pickens 230 kV Substation is a 225.0 MW solar interconnection project in Holmes, Mississippi with a current status of operational. It is proposed to connect at Pickens 230 kV Substation.

225.0 MWCapacity
OperationalStatus
Market
SolarTechnology

Project facts

Canonical namePickens 230 kV Substation
Queue IDJ3139
Statusoperational
Source statusPending Revision Approval
Market
TechnologySolar
Capacity225.0 MW
StateMississippi
CountyHolmes
Point of interconnectionPickens 230 kV Substation
Requested (queue) date2022-09-13
Proposed in-service date2026-06-30
Operational date2026-06-30
Withdrawn date
Developer
Utility / transmission ownerENTERGY ARKANSAS

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata