PJM-WEC (AI1-047 5189719)

PJM-WEC is a 314.0 MW gas interconnection project with a current status of withdrawn.

314.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical namePJM-WEC
Queue IDAI1-047 5189719
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity314.0 MW
StateN/A
CountyN/a
Point of interconnection
Requested (queue) date2022-05-26
Proposed in-service date
Operational date
Withdrawn date2022-09-14
Developer
Utility / transmission ownerPJM

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata