Post Oak 69kV (GEN-2017-177)

Post Oak 69kV is a 40.0 MW solar interconnection project in Post Oak, Missouri with a current status of withdrawn. It is proposed to connect at Post Oak 69kV.

40.0 MWCapacity
WithdrawnStatus
MOMarket
SolarTechnology

Project facts

Canonical namePost Oak 69kV
Queue IDGEN-2017-177
Statuswithdrawn
Source statusWITHDRAWN
MarketMO
TechnologySolar
Capacity40.0 MW
StateMissouri
CountyPost Oak
Point of interconnectionPost Oak 69kV
Requested (queue) date2017-11-29
Proposed in-service date
Operational date
Withdrawn date2020-08-17
Developer
Utility / transmission ownerSPP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.