NV Energy Queue Project 26-00473 — Battery in Clark, the U.S.

NV Energy Queue Project 26-00473 — Battery in Clark, the U.S. is a 300.0 MW battery interconnection project with a current status of active. It is proposed to connect at Reid Gardner 230 kV.

300.0 MWCapacity
ActiveStatus
Market
BatteryTechnology

Project facts

Canonical nameNV Energy Queue Project 26-00473 — Battery in Clark, the U.S.
Queue ID26-00473
Statusactive
Source statusIn Study
Market
TechnologyBattery
Capacity300.0 MW
State
CountyClark
Point of interconnectionReid Gardner 230 kV
Requested (queue) date2026-07-30
Proposed in-service date2028-01-01
Operational date
Withdrawn date
Developer
Utility / transmission ownerNV Energy (Nevada Power / Sierra Pacific Power)

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.