NV Energy Queue Project 26-00487 — Solar+Battery in Esmeralda, the U.S.

NV Energy Queue Project 26-00487 — Solar+Battery in Esmeralda, the U.S. is a 600.0 MW solar+battery interconnection project with a current status of active. It is proposed to connect at Esmeralda 500kV.

600.0 MWCapacity
ActiveStatus
Market
Solar+BatteryTechnology

Project facts

Canonical nameNV Energy Queue Project 26-00487 — Solar+Battery in Esmeralda, the U.S.
Queue ID26-00487
Statusactive
Source statusIn Study
Market
TechnologySolar+Battery
Capacity600.0 MW
State
CountyEsmeralda
Point of interconnectionEsmeralda 500kV
Requested (queue) date2026-07-30
Proposed in-service date2032-09-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerNV Energy (Nevada Power / Sierra Pacific Power)

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-10new_projectactivehigh

Explore related data

Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-27

Provenance: nvenergy-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata