Arizona Public Service Queue Project Q300 — Battery in Maricopa Az, the U.S. is a 17.0 MW battery interconnection project with a current status of active. It is proposed to connect at Center 12kV.
17.0 MWCapacity
ActiveStatus
—Market
BatteryTechnology
Project facts
| Canonical name | Arizona Public Service Queue Project Q300 — Battery in Maricopa Az, the U.S. |
|---|---|
| Queue ID | Q300 |
| Status | active |
| Source status | Interconnection Network |
| Market | — |
| Technology | Battery |
| Capacity | 17.0 MW |
| State | — |
| County | Maricopa Az |
| Point of interconnection | Center 12kV |
| Requested (queue) date | 2019-03-29 |
| Proposed in-service date | 2022-05-01 |
| Operational date | — |
| Withdrawn date | — |
| Developer | — |
| Utility / transmission owner | Arizona Public Service |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-10 | poi_name | Cotton Center 12kV | Center 12kV | low |
| 2026-08-10 | operational_date | 2022-05-01 | — | medium |
| 2026-08-10 | proposed_online_date | — | 2022-05-01 | medium |
| 2026-08-10 | status | operational | active | high |
| 2026-08-03 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-24
Data last materially changed2026-08-24
Page data generated2026-08-28
Provenance: aps-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata